Kurti Launches €700,000 Sitnica Bridge Reconstruction in Mitrovica, Following Series of Infrastructure Projects

RksNews
RksNews 5 Min Read
5 Min Read

Kosovo Prime Minister Albin Kurti on Monday laid the foundation stone for the reconstruction of a bridge over the Sitnica River in South Mitrovica, in a project worth €700,000.

The investment marks another infrastructure project involving Mitrovica’s bridges, following the construction of two new bridges over the Ibër River last year and the ongoing construction of a third bridge near Zhabare.

Kurti attended the ceremony alongside South Mitrovica Mayor Faton Peci and Minister of Local Government Administration Elbert Krasniqi.

The €700,000 project is being jointly financed by the Ministry of Local Government Administration and the Municipality of South Mitrovica.

“Today, we laid the foundation stone for this important project, worth a total of €700,000, jointly financed by the Ministry of Local Government Administration and the Municipality of Mitrovica,” Kurti said.

Referring to the government’s investments in bridge infrastructure, the prime minister said that construction was being carried out across Kosovo, but with particular focus on areas where bridges had previously been lacking.

“We are building bridges throughout Kosovo, but, of course, more, faster and more frequently in places where they were previously missing — and Mitrovica is precisely such a place,” Kurti stated.

He said work on the Sitnica bridge had already begun and expressed expectations that the reconstructed structure would be opened soon.

Mayor Faton Peci described the bridge as an important crossing at one of the main entrances to South Mitrovica, saying the reconstruction would give it a new appearance while making it safer and more functional.

However, Peci presented Monday’s event on social media as the opening of the bridge, while Kurti and the Prime Minister’s Office confirmed that the ceremony marked the beginning of reconstruction works, not their completion.

Two Ibër bridges completed at a cost of nearly €3 million

The Sitnica project follows a series of bridge construction and reconstruction investments in Mitrovica.

On July 1, 2025, Kurti laid the foundation stone for two new bridges over the Ibër River: one designed for vehicles and pedestrians, and another exclusively for pedestrians.

Both bridges were completed last year, with their combined contracted value reaching €2,999,628.18.

The projects also attracted scrutiny over individual budget allocations. According to the financial breakdown published at the time, €200,000 was allocated for the temporary diversion of the river, €150,000 for site cleaning, €50,000 for geodetic measurements and another €75,000 for final project documentation.

The news portal Demokracia also questioned the procurement procedure, reporting that a negotiated procedure without publication of a tender had been used. The portal further reported that prosecutors had launched an investigation into the tender.

Third bridge near Zhabare expected to be completed by the end of 2026

Meanwhile, construction is underway on a third bridge over the Ibër River, near Zhabare.

During a visit to the construction site on August 4, Kurti said the project could be completed by the end of 2026.

According to the plans presented at the time, the bridge will be 65 metres long and 22.5 metres wide, featuring four traffic lanes and pedestrian pavements on both sides.

The project also includes two roundabouts, a 500-metre access road and regulation of a 525-metre section of the riverbed.

Then acting Minister of Infrastructure Dimal Basha highlighted the bridge’s security importance, saying it would allow security and law enforcement institutions to gain “faster and easier access from both sides of the Ibër.”

Sitnica reconstruction brings total investment close to €3.7 million

The reconstruction of the Sitnica bridge is the fourth bridge-related project highlighted by Kurti’s government in Mitrovica, following the completion of two bridges over the Ibër and the ongoing construction of the third near Zhabare.

Unlike the three Ibër projects, the Sitnica initiative involves the reconstruction of an existing bridge rather than the construction of a new one.

With the latest €700,000 investment, the combined value of the two completed Ibër bridges and the announced Sitnica reconstruction reaches nearly €3.7 million. This figure does not include the cost of the third bridge near Zhabare.

Kurti said bridge infrastructure was particularly important for Mitrovica, reiterating that two bridges over the Ibër had been completed last year while another remains under construction.

The Sitnica reconstruction is expected to improve traffic safety and functionality at one of the main access points to South Mitrovica.