The Ministry of Infrastructure and Transport has announced that works are continuing on the Livadhet e Istogut – Mokna road project.
According to the ministry’s announcement, based on the current pace of construction, the project is expected to be completed within this year.
Ministry statement:
Works are continuing on the Livadhet e Istogut – Mokna road project.
Based on the current dynamics of the works, the project is expected to be completed by the end of this year.
In Phase II, approximately 8.2 kilometers have been asphalted so far, while around 3.7 kilometers remain to be asphalted. In Phase I, the works have been completed to approximately 90%.
Phase I
- Contract value: €855,185.02
- Road length: 7,266 meters
Phase II
- Contract value: €2,844,411.83
- Road length: 11,907 meters
In total, the Municipality of Istog will benefit from a road project stretching nearly 20 kilometers, with a total investment value of €3,699,596.85.
This investment will significantly improve road infrastructure, increase traffic safety, and create better conditions for movement for residents and all users of this road.